Relocation of Ihwagi Intake

Project Detail Report

Overview

StatusCompleted
TypeWater Supply
AgencyTana Water Works Development Agency
ProgramWater Harvesting Programme
Progress100.00%

Location Information

CountyNyeri
ConstituencyMathira
WardIriani
SettingRural
Coordinates0.633361, 36.633361

Timeline & Impact

Start Date2023-06-06
Planned End Date2024-07-06
Actual End DateN/A
ContractorSori Investment Ltd
ConsultantN/A
Target AreasKaratina Town and its Environs
Scope of Works Construction of new intake and inlet chamber  Laying of raw water gravity mainline  Construction of 10m3 Break Pressure Tank (BPT)
ImpactsThe project has facilitated farming activity within the area.
ChallengesLate GOK disbursement and contactor citing financial constrains.
RemarksImproving access to safe water for domestic use.

Project Cost

Total Contract Sum (GoK + Foreign)KES 42,949,940.00
GoK Contract SumKES 42,949,940.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 34,724,200.00
Outstanding CostKES 8,225,740.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 42,949,940.00

Beneficiaries

Target Households800
Target Population4,000