Desludging of Kiaigi waste water treatment plant

Project Detail Report

Overview

StatusCompleted
TypeSanitation
AgencyTana Water Works Development Agency
ProgramUniversal Health Coverage
Progress100.00%

Location Information

CountyNyeri
ConstituencyMathira
WardKaratina Town
SettingUrban
Coordinates0.483200, 37.127400

Timeline & Impact

Start Date2023-08-02
Planned End Date2024-09-02
Actual End Date2024-08-06
ContractorMacplan Engineering Ltd
ConsultantN/A
Target AreasKaratina Town
Scope of Works De-sludging of primary and secondary ponds, slopes reinstatement, lighting improvement.
ImpactsThe project has facilitated access to clean water and provision of emplyment to locals.
ChallengesLate GOK disbursement and contactor citing financial constrains.
RemarksImproving access to safe water for domestic use.

Project Cost

Total Contract Sum (GoK + Foreign)KES 34,602,956.24
GoK Contract SumKES 17,301,478.12
Foreign Contract SumKES 17,301,478.12
Cumulative ExpenditureKES 33,085,448.12
Outstanding CostKES 1,517,508.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 17,301,478.12