| Start Date | 2023-03-06 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Power and Solar Group Limited |
| Consultant | N/A |
| Target Areas | Endarasha and its environs |
| Scope of Works | - Laying of a 7.1km Kamianda-Endarasha mainline.
- Laying of 1.48km Endarasha-Kanyiriri mainline.
- Laying of 4.4km Kamigogo intake to Charity
- Construction of 2 No 5m3 Break Pressure Tanks (BPT).
- Rehabilitation of 2 No existing tanks to serve as Break Pressure Tanks. |
| Impacts | Provision od emplyment. More than 1300 Households will stand to benefit from the project |
| Challenges | Slow progress by the contractor citing financial constraints |
| Remarks | Improvement acees to clean water |