Baraka-Chaka/Tagwa Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply
AgencyTana Water Works Development Agency
ProgramCross-County Programme
Progress80.00%

Location Information

CountyNyeri
ConstituencyKieni
WardRuringu
SettingRural
Coordinates0.500000, 37.333330

Timeline & Impact

Start Date2023-07-06
Planned End Date2025-06-06
Actual End DateN/A
ContractorOctagon
ConsultantN/A
Target AreasChaka Town and envrons
Scope of Works·     Supply and installation of surface pump, motor and electrical power connection ·     Laying of rising main Construction of 500m3 ground high tensile steel water tank
ImpactsImprove access to clean water
ChallengesSlow progress by the contractor citing financial constraints
RemarksImprovement acees to clean water

Project Cost

Total Contract Sum (GoK + Foreign)KES 63,515,714.68
GoK Contract SumKES 63,515,714.68
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 63,515,714.68

Beneficiaries

Target Households3,000
Target Population15,000