Overview
| Status | Completed |
| Type | Water Supply |
| Agency | Tana Water Works Development Agency |
| Program | Cross-County Programme |
| Progress | 100.00% |
Location Information
| County | Meru |
| Constituency | Tigania West |
| Ward | Nkomo |
| Setting | Rural |
| Coordinates | 0.197650, 37.790390 |
Timeline & Impact
| Start Date | 2020-11-09 |
| Planned End Date | 2021-05-08 |
| Actual End Date | 2021-05-08 |
| Contractor | Shaljo Enterprises Limited. |
| Consultant | N/A |
| Target Areas | Nkomo |
| Scope of Works | Laying of 2No. 2.58km parallel lines225 mm and 110 mm |
| Impacts | Provision of reliable water for domestic and agricultural use. |
| Challenges | GOK late disbursments |
| Remarks | Complete |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 8,499,205.00 |
| GoK Contract Sum | KES 8,499,205.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 5,739,440.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
8,499,205.00 |
Beneficiaries
| Target Households | 500 |
| Target Population | 2,500 |