Thangatha Dam Spillway Repairs

Project Detail Report

Overview

StatusCompleted
TypeDam
AgencyTana Water Works Development Agency
ProgramWater Harvesting Programme
Progress100.00%

Location Information

CountyMeru
ConstituencyTigania East
WardThangatha
SettingRural
Coordinates0.083330, 38.166670

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorAMG Sagirin LTD
ConsultantN/A
Target AreasThangatha
Scope of Works Repair of spillway
ImpactsProvision of reliable water for domestic and agricultural use.
ChallengesGOK late disbursments
RemarksRepairs completed, however assessment carried out for remedial works following damage by El Nino floods.

Project Cost

Total Contract Sum (GoK + Foreign)KES 3,317,600.00
GoK Contract SumKES 3,317,600.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,317,600.00

Beneficiaries

Target Households250
Target Population1,250