| Start Date | 2024-05-06 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Finscope Investment |
| Consultant | N/A |
| Target Areas | Maritati police post maritati vilaage Maritati dispensary and Maritati market |
| Scope of Works | Drilling, development and test pumping
Borehole drilled to 147.9m and 40m3/h yield obtained
Equipping with solar powered associated works
Last mile connectivity |
| Impacts | The project will benefit the people of Maritati, Maritati Police, Maritati dispensary and Maritati Market |
| Challenges | Slow progress due to Financial constrains from the contractor |
| Remarks | Tthre is need for coordination and follow up on contractor's program of work for the project to be completed on time. |