Print / Save to PDF
Close
Overview
Status Proposed
Type Sanitation Project
Agency Tana Water Works Development Agency
Program PPP
Progress 0.00%
Location Information
County Meru
Constituency Tigania West
Ward Nkomo
Setting Urban
Coordinates ,
Timeline & Impact
Start Date N/A
Planned End Date N/A
Actual End Date N/A
Contractor TBD
Consultant TBD
Target Areas Nkubu town and its environs
Scope of Works ▪ Construction of 3,000m3/day wastewater stabilization ponds
-Laying of 13.3km trunk main (DN 600-320mm)
- Laying of 20.8km laterals and secondaries (DN 450-300mm
- Last Mile Connectivity
Impacts Provision of reliable sanitation facility
Challenges Awaiting Funds allocation
Remarks Project designed
Project Cost
Total Contract Sum (GoK + Foreign) KES 850,000,000.00
GoK Contract Sum KES 850,000,000.00
Foreign Contract Sum KES 0.00
Cumulative Expenditure KES 0.00
Outstanding Cost KES 0.00
Beneficiaries
Target Households 800
Target Population 4,000