Kimbimbi Sub- County Hospital

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyTana Water Works Development Agency
ProgramUniversal Health Coverage
Progress63.00%

Location Information

CountyKirinyaga
ConstituencyMwea
WardNyangati
SettingUrban
Coordinates-0.619697, 37.370919

Timeline & Impact

Start Date2021-09-02
Planned End DateN/A
Actual End DateN/A
ContractorOctagon Builders & General Suppliers
ConsultantN/A
Target AreasKimbimbi Hospital
Scope of Works Connect to Mwea Makima Water system 2.5km away;  Erection of 50m3; Pressed Steel Elevated Tank;  Improvement of rain water harvesting facilities
ImpactsProvision of safe water
ChallengesGOK late disbursments . Contractor citing financial constraints
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 7,113,109.00
GoK Contract SumKES 7,113,109.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 3,874,611.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 7,113,109.00

Beneficiaries

Target Households1
Target Population500