Ngariama Njukiini Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply Project
AgencyTana Water Works Development Agency
ProgramDrought Intervention/Mitigation Program
Progress23.00%

Location Information

CountyKirinyaga
ConstituencyGichugu
WardNgariama
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorAlwahab Enterprises Ltd
ConsultantN/A
Target AreasGichugu
Scope of Works Construction of 1 no. Cross weir and an intake chamber.  Laying DN 280 mm – 6.36 km long raw water gravity main  Treatment works capacity 4,200m3 per day  DN 450/315/280/225mm – Treated Water Gravity Mains  DN 160-110mm-8.5 km distribution pipelines.  1 No. -225m3 Clear Water Tank at the Treatment Works. Rehabilitation of 3No. Ground Masonry Tanks.
ImpactsProvision of safe water
ChallengesGOK late disbursments . Contractor citing financial constraints
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 268,100,101.50
GoK Contract SumKES 268,100,101.50
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 35,596,718.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 268,100,101.50

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved GOK 50,000,000.00
2023/24 Approved GOK 135,000,000.00
2024/25 Allocated GOK 80,000,000.00

Beneficiaries

Target Households14,000
Target Population70,000