Kerugoya Sewerage Project (Last mile connectivity)

Project Detail Report

Overview

StatusProposed
TypeSanitation Project
AgencyTana Water Works Development Agency
ProgramNational Urban Water Supply and Sanitataion Program (NUWASSAP) Lot I
Progress0.00%

Location Information

CountyKirinyaga
ConstituencyKirinyaga Central
WardTBD
SettingUrban
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorTBD
ConsultantTBD
Target AreasKerugoya, Kutus and Kagio
Scope of Works▪ Laying secondary sewer lines DWC of Diameter 200mm and 300mm ▪ Construction of the connection manholes.
ImpactsProvision of safe and reliable sanitation services
ChallengesDelay may happen due to unavailability of funds
RemarksDesigns complete and earmarked to commence soon

Project Cost

Total Contract Sum (GoK + Foreign)KES 290.00
GoK Contract SumKES 290.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households4,000
Target Population20,000