Kianyaga Sewerage Project

Project Detail Report

Overview

StatusProposed
TypeSanitation Project
AgencyTana Water Works Development Agency
ProgramNational Urban Water Supply and Sanitataion Program (NUWASSAP) LOT II
Progress0.00%

Location Information

CountyKirinyaga
ConstituencyGichugu
WardTBD
SettingUrban
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorTBD
ConsultantTBD
Target AreasKianyaga and Environs
Scope of Works▪ Laying of 16.5km sewerline- 200mm-400mm.
ImpactsProvision of safe and reliable sanitation services
ChallengesFunds unavailabilty
RemarksDesign, ESIA AND RAP activities for the project is ongoing.

Project Cost

Total Contract Sum (GoK + Foreign)KES 239.00
GoK Contract SumKES 239.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households1,000
Target Population5,000