Siakago Girls Secondary School Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTana Water Works Development Agency
ProgramWater for Schools
Progress100.00%

Location Information

CountyEmbu
ConstituencyMbeere South
WardRuguru/ngandori
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End Date2020-08-07
Actual End Date2021-04-11
ContractorYarrow Construction Ltd Maxwell Green Ltd.
ConsultantN/A
Target AreasSiakago Girls Secondary School
Scope of Works Drilling, development, test pumping and equipping with solar powered pumping system  Borehole drilled to 180m depth - 4m3/h yield obtained
ImpactsImproves access to clean water and create employment opportunities
ChallengesLate disbursement of government funds.
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 6,335,010.62
GoK Contract SumKES 6,335,010.62
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 3,056,570.00
Outstanding CostKES 3,278,440.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 6,335,010.62