Kasafari Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTana Water Works Development Agency
ProgramCross-County Programme
Progress100.00%

Location Information

CountyEmbu
ConstituencyRunyenjes
WardGaturi North
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End Date2021-06-02
Actual End DateN/A
ContractorOctagon Builders and General Supplies Central Water Company Limited
ConsultantN/A
Target AreasKasafari Community
Scope of Works Drilling, development, test pumping and equipping with solar powered pumping system  Borehole drilled to 256m depth - 8m3/h yield obtained
ImpactsImproves access to clean water AND create employment opportunities
ChallengesLate disbursement of government funds.
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 4,871,504.00
GoK Contract SumKES 4,871,504.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 3,866,452.00
Outstanding CostKES 1,005,052.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 4,871,504.00

Beneficiaries

Target Households60
Target Population300