Runyenjes TVET Borehole

Project Detail Report

Overview

StatusCompleted
TypeBorehole
AgencyTana Water Works Development Agency
ProgramWater for Schools
Progress100.00%

Location Information

CountyEmbu
ConstituencyRunyenjes
WardGaturi North
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End Date2021-03-02
Actual End DateN/A
ContractorOctagon Builders and General Supplies , Export-Hydro Pump and Service Ltd.
ConsultantN/A
Target AreasRunyenjes TVET and the surrounding Community
Scope of Works Drilling, development, test pumping and equipping with solar powered pumping system
ImpactsImproves access to clean water and create employment opportunities
ChallengesLate disbursement of government funds.
RemarksNeed for Improved Coordination and Timely Funding

Project Cost

Total Contract Sum (GoK + Foreign)KES 5,071,511.00
GoK Contract SumKES 5,071,511.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 4,407,923.51
Outstanding CostKES 663,587.49

Funding Sources

SourceTypeAmount (KES)
Gok Grant 5,071,511.00

Beneficiaries

Target Households1
Target Population1,000