Munyiri Dam

Project Detail Report

Overview

StatusProposed
TypeDam
AgencyTana Water Works Development Agency
ProgramCross-County Programme
Progress0.00%

Location Information

CountyEmbu
ConstituencyMbeere South
WardNthawa
SettingRural
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasMunyiri area and its envrons
Scope of WorksTBD
ImpactsImproves access to clean water and create employment opportunities
ChallengesLack of GOK funds may delay commencement of the works
RemarksFeasibility Study done waiting for the Final Designs

Project Cost

Total Contract Sum (GoK + Foreign)KES 60.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 60.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households40
Target Population200