Chogoria Sewerage Project

Project Detail Report

Overview

StatusOngoing
TypeSewerage Project
AgencyTana Water Works Development Agency
ProgramKenya Towns Sustainable Water Supply and Sanitation Programme
Progress1.00%

Location Information

CountyTharaka Nithi
ConstituencyMaara
WardChogoria and Mwimbi
SettingUrban
Coordinates,

Timeline & Impact

Start Date2019-02-01
Planned End DateN/A
Actual End DateN/A
ContractorZhong Hao Overseas Construction Engineering Company Ltd.
ConsultantIB Mangat Consultant
Target AreasChogoria town and envron
Scope of WorksTrunk sewer 16 km dia ranging from 300-375mm, ● Secondary sewers 7.6 km Dia 225mm Sewage treatment works capacity-1100m3/day
ImpactsThere is improved wastewater management for the Chogoria town and Environs • Creation of the works for the new staff for this plant ( 15 new staff employed) • Increased Revenue for the WSP"
ChallengesThis being the first Sewerage plant for the WSP, they had Capacity issue on handling it upon works completion , but they have engage qualified staff to assist for the works
RemarksThe Project is complete and operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 374,595,276.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 374,595,276.00
Cumulative ExpenditureKES 353,879,827.40
Outstanding CostKES 41,528,522.47

Funding Sources

SourceTypeAmount (KES)
Adb Loan 374,595,276.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 96,601,331.27
2021/22 Approved GOK 41,442,000.00
2022/23 Approved FOREIGN 96,601,331.27
2022/23 Approved GOK 35,000,000.00
2023/24 Approved FOREIGN 73,726,365.52
2023/24 Approved GOK 44,000,000.00
2024/25 Allocated FOREIGN 48,000,000.00
2024/25 Allocated GOK 15,000,000.00

Beneficiaries

Target Households6,000
Target Population6,000