Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Sewerage Project |
| Agency | Tana Water Works Development Agency |
| Program | Kenya Towns Sustainable Water Supply and Sanitation Programme |
| Progress | 1.00% |
| County | Tharaka Nithi |
|---|---|
| Constituency | Maara |
| Ward | Chogoria and Mwimbi |
| Setting | Urban |
| Coordinates | , |
| Start Date | 2019-02-01 |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Zhong Hao Overseas Construction Engineering Company Ltd. |
| Consultant | IB Mangat Consultant |
| Target Areas | Chogoria town and envron |
| Scope of Works | Trunk sewer 16 km dia ranging from 300-375mm, ● Secondary sewers 7.6 km Dia 225mm Sewage treatment works capacity-1100m3/day |
| Impacts | There is improved wastewater management for the Chogoria town and Environs • Creation of the works for the new staff for this plant ( 15 new staff employed) • Increased Revenue for the WSP" |
| Challenges | This being the first Sewerage plant for the WSP, they had Capacity issue on handling it upon works completion , but they have engage qualified staff to assist for the works |
| Remarks | The Project is complete and operational |
| Total Contract Sum (GoK + Foreign) | KES 374,595,276.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 374,595,276.00 |
| Cumulative Expenditure | KES 353,879,827.40 |
| Outstanding Cost | KES 41,528,522.47 |
| Source | Type | Amount (KES) |
|---|---|---|
| Adb | Loan | 374,595,276.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 96,601,331.27 |
| 2021/22 | Approved | GOK | 41,442,000.00 |
| 2022/23 | Approved | FOREIGN | 96,601,331.27 |
| 2022/23 | Approved | GOK | 35,000,000.00 |
| 2023/24 | Approved | FOREIGN | 73,726,365.52 |
| 2023/24 | Approved | GOK | 44,000,000.00 |
| 2024/25 | Allocated | FOREIGN | 48,000,000.00 |
| 2024/25 | Allocated | GOK | 15,000,000.00 |
| Target Households | 6,000 |
|---|---|
| Target Population | 6,000 |