Chogoria Last Mile Water Project

Project Detail Report

Overview

StatusProposed
TypeWater Supply Project
AgencyTana Water Works Development Agency
ProgramNational Urban Water Supply and Sanitataion Program (NUWASSAP) Lot I
Progress0.00%

Location Information

CountyTharaka Nithi
ConstituencyMaara
WardMitheru
SettingUrban
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorN/A
ConsultantN/A
Target AreasChogoria Town and its environs
Scope of Worksi) Laying of 80km reticulation network comprising of pipes ranging from DN 110m-50mm diameter ii) Construction of 5,000 household water connections complete with metering
ImpactsImproves access to clean water and create employment opportunities
ChallengesDelay to have the works commence
RemarksDesigns complete and earmarked to commence soon

Project Cost

Total Contract Sum (GoK + Foreign)KES 205,000,000.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 205,000,000.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households2,000
Target Population10,000