Overview
| Status | Proposed |
| Type | Water Supply Project |
| Agency | Tana Water Works Development Agency |
| Program | Cross-County Programme |
| Progress | 0.00% |
Location Information
| County | Tharaka Nithi |
| Constituency | Chuka/Igambang’ombe |
| Ward | Igambang’ombe Ward |
| Setting | Rural |
| Coordinates | , |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Kanjuki area and its envrons |
| Scope of Works | Laying of 10km reticulation network comprising of pipes ranging from DN 110m-63mm diameter. |
| Impacts | Improves access to clean water and create employment opportunities |
| Challenges | Delay for funds to implement this project |
| Remarks | Project at Design Stage |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 30,000,000.00 |
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 30,000,000.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 900 |
| Target Population | 4,500 |