Overview
| Status | Proposed |
| Type | Water Supply Project |
| Agency | Tana Water Works Development Agency |
| Program | Cross-County Programme |
| Progress | 0.00% |
Location Information
| County | Tharaka Nithi |
| Constituency | Tharaka |
| Ward | Mitheru |
| Setting | Urban |
| Coordinates | 0.293000, 37.675900 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Mitheru ward |
| Scope of Works | ยท Rehabilitation of pipeline Laying of water distribution pipe network |
| Impacts | Improves access to clean water and create employment opportunities |
| Challenges | Delay may happen due to unavailability of funds |
| Remarks | Preliminary Designs Done |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 70,000,000.00 |
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 70,000,000.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 3,000 |
| Target Population | 600 |