Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Borehole |
| Agency | Central Rift Valley Water Works Development Agency |
| Program | Equalization Fund Project Phase ll |
| Progress | 50.00% |
| County | Mombasa |
|---|---|
| Constituency | Likoni |
| Ward | Shika adabu |
| Setting | Rural |
| Coordinates | 3.121800, 35.587200 |
| Start Date | 2024-07-03 |
|---|---|
| Planned End Date | 2024-10-03 |
| Scope of Works | Drilling, Equipping and Civil Works |
| Impacts | Improve access to water |
| Challenges | Contractor facing finanancial challanges |