Cheminya Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeRiver Intake
AgencyNorth Rift Valley Water Works Developmnet Agency
ProgramNorth Rift Valley WWDA Projects
Progress90.00%

Location Information

CountyElgeyo-Marakwet
ConstituencyKeiyo South
WardKaptarakwa
SettingRural
Coordinates,

Timeline & Impact

Start Date2023-11-03
Planned End Date2024-11-09
Actual End DateN/A
ContractorKhadim Co. Ltd
ConsultantN/A
Target AreasKitany/Chepteran Environs.
Scope of WorksRehabilitation of existing dam, solarization, laying of 10Km pipelines
ImpactsIncreased water coverage Improved Quality of Life Reduction in Waterborne Diseases Better Hygiene and Sanitation Increased Productivity Community Cohesion Reforestation and Soil Conservation
ChallengesIssues between the project host community and the immediate neighbouring community on the source of water and extent of coverage
RemarksProject on schedule

Project Cost

Total Contract Sum (GoK + Foreign)KES 26,680,500.00
GoK Contract SumKES 26,680,500.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 13,680,000.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 30,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 30,000,000.00

Beneficiaries

Target Households720
Target Population3,600