Mois Bridge Matunda Water Supply Project

Project Detail Report

Overview

StatusOngoing
TypeWater Supply
AgencyNorth Rift Valley Water Works Developmnet Agency
ProgramNorth Rift Valley WWDA Projects
Progress5.00%

Location Information

CountyUasin Gishu, Kakamega & Trans Nzoia
ConstituencySoy, Cherangany & Lukuyani
WardMoi's Bridge
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorBlue Swift Contractors and General Supplies Limited
ConsultantProfessional Consultants in association with Kagga and partners
Target AreasMois Bridge and Matunda
Scope of WorksConstruction of the Intake weir on Chepkaitit River Laying of Raw Water Mains Nominal Diameter 400m Construction of Water Treatment Works with a daily production capacity of 14,270m3/day Laying of 73.9km transmission pipelines in sizes ranging from nominal diameter 315-110 Laying of 105.3km distribution pipelines in sizes ranging from nominal diameter 200-50 Construction of 2no. masonry storage tanks & rehabilitation of 6no. masonry tanks total capacity 1,550m3 Construction of 1500m3 and 500m3 concrete tanks at Maji mazuri and Milimani Construction of 11no. water kiosks
ImpactsNIL
ChallengesNIL
RemarksThe contractor has mobilized to site and prepared access roads to both intake and Treatment Works sites

Project Cost

Total Contract Sum (GoK + Foreign)KES 1,921,422,451.00
GoK Contract SumKES 1,921,422,451.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 200,000,000.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 200,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 200,000,000.00

Beneficiaries

Target Households20,638
Target Population0