Overview
| Status | Completed |
| Type | Borehole |
| Agency | North Rift Valley Water Works Developmnet Agency |
| Program | North Rift Valley WWDA Projects |
| Progress | 100.00% |
Location Information
| County | Uasin Gishu |
| Constituency | Soy |
| Ward | Kamagut |
| Setting | Rural |
| Coordinates | , |
Timeline & Impact
| Start Date | 2023-11-05 |
| Planned End Date | 2023-11-10 |
| Actual End Date | N/A |
| Contractor | Top Mast
Engineering |
| Consultant | N/A |
| Target Areas | Kamoret /Kamagut Community |
| Scope of Works | Drilling, equiping and solarization of the borehole. Construction of elevated tank and distribution network. |
| Impacts | NIL |
| Challenges | Saline water |
| Remarks | Phase 1 complete |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 11,454,300.00 |
| GoK Contract Sum | KES 11,454,300.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 7,917,930.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 300 |
| Target Population | 2,000 |