Project Detail Report
| Status | Proposed |
|---|---|
| Type | Unknown |
| Agency | North Rift Valley Water Works Developmnet Agency |
| Program | North Rift Valley WWDA Projects |
| Progress | 0.00% |
| County | N/A |
|---|---|
| Constituency | N/A |
| Ward | N/A |
| Setting | N/A |
| Coordinates | , |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | Eldoret Municipality and its environs |
| Scope of Works | • Construction of a new 38m high Roller compacted Concrete dam 500m downstream of the existing Two Rivers Dam • Laying of Gravity main size 1000mm, length 1.5km to Sosiani Treatment Plant • Rehabilitation of the existing Sosiani Treatment plant back to design capacity of 14,000m3/day • Construction of new Treatment Plant of Capacity 62,000m3/day adjacent to the existing Sosiani Treatment Plant • Relocation of about 2.km of Railway Line |
| Impacts | NIL |
| Challenges | NIL |
| Remarks | Detailed design and tender documents prepared. Project identified as one to be undertaken under PPP model. Design submitted to Maji House |
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Target Households | 100,000 |
|---|---|
| Target Population | 0 |