Fofen Dam

Project Detail Report

Overview

StatusCompleted
TypeDam
AgencyNorthern Water Works Development Agency
ProgramNorthern WWDA Projects
Progress100.00%

Location Information

CountyMarsabit
ConstituencyLaisamis
WardKorr
SettingN/A
Coordinates,

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End Date2027-01-10
ContractorBluemagic Limited
ConsultantN/A
Target AreasNIL
Scope of WorksNIL
ImpactsTo Increase water storage to be used in dry periods to reduce the cost of living and inclusive growth
ChallengesInsufficient budgetary allocations
RemarksNIL

Project Cost

Total Contract Sum (GoK + Foreign)KES 0.00
GoK Contract SumKES 0.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households200
Target Population1,200