Overview
| Status | Ongoing |
| Type | Water Supply |
| Agency | Northern Water Works Development Agency |
| Program | Construction of Water Pans and Small Dams: |
| Progress | 1.00% |
Location Information
| County | Garissa |
| Constituency | Township |
| Ward | Iftin |
| Setting | N/A |
| Coordinates | , |
Timeline & Impact
| Start Date | 2024-04-01 |
| Planned End Date | N/A |
| Actual End Date | 2024-01-10 |
| Contractor | MH Young Construction Co Ltd |
| Consultant | N/A |
| Target Areas | N/A |
| Scope of Works | Drilling and Equipping of borehole, Construction of 50m3 Elevated Steel Tank, Laying of Distribution Mains, Consumer Connections |
| Impacts | To increase water Supply to human and Livestock |
| Challenges | Insufficient budgetary allocations |
| Remarks | N/A |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
Beneficiaries
| Target Households | 200 |
| Target Population | 1,200 |