LOT 1-Construction of CBD and industrial Area sewers

Project Detail Report

Overview

StatusOngoing
TypeSewer construction
AgencyAthi Water Works Development Agency
ProgramNairobi City Regeneration programme
Progress89.00%

Location Information

CountyNairobi
ConstituencyMakadara
WardViwandani ward
SettingUrban
Coordinates-1.308793, 36.868480

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorJoint commercial Suppliers
ConsultantEngplan consulting engineers
Target AreasNestle kenya, pate, Sacio road, Sekondi road, Pate
Scope of Worksconstruction of 500m of DN 375mm spigot and socket concrete pipe sewers, 3850 DN 450, 1050 DN 600, construction of precast manholes and backdrops, nominal bore 1050 and 1200mm, sewer and manhole unblocking, desilting and cleaning, Micro-tunneling( DN 225-DN 600) of various roads in Nairobi City
ImpactsImproved sanitation
Challengesworked was temporarily stalled on rainy days, but generally the project was smooth
RemarksN/A

Project Cost

Total Contract Sum (GoK + Foreign)KES 236,669,545.20
GoK Contract SumKES 236,669,545.20
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 126,502,163.00
Outstanding CostKES 110,167,382.20

Funding Sources

SourceTypeAmount (KES)
Gok Grant 236,669,545.20

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved GOK 64,107,345.20
2022/23 Approved GOK 32,053,672.60
2023/24 Approved GOK 48,080,508.90