Project Detail Report
| Status | Ongoing |
|---|---|
| Type | Unknown |
| Agency | Athi Water Works Development Agency |
| Program | Nairobi Rivers Basin Rehabilitation and Restoration Program: Sewerage Improvement Project Phase II |
| Progress | 93.00% |
| County | Kiambu |
|---|---|
| Constituency | Ruiru |
| Ward | Kahawa Sukari, Gatongora, Mugutha |
| Setting | Urban |
| Coordinates | -1.190403, 36.935342 |
| Start Date | N/A |
|---|---|
| Planned End Date | 2024-08-07 |
| Actual End Date | N/A |
| Contractor | 15/03/2023 |
| Consultant | 14/09/2024 |
| Target Areas | 47520 |
| Scope of Works | Laying 65.6km of Sewer Line with sizes ranging from 225mm to 450mm, construction of 1,608no. manholes, construction of 1,209no. household chambers, improved inlet works capacity 31,500m3/day, Construction of 1no. Faecal Discharge Point |
| Impacts | N/A |
| Challenges | N/A |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 522,686,570.35 |
|---|---|
| GoK Contract Sum | KES 83,629,851.25 |
| Foreign Contract Sum | KES 439,056,719.10 |
| Cumulative Expenditure | KES 52,285,978.69 |
| Outstanding Cost | KES 478,141,052.08 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 177,276,600.00 |
| 2021/22 | Approved | GOK | 9,848,700.00 |
| 2022/23 | Approved | FOREIGN | 152,162,415.00 |
| 2022/23 | Approved | GOK | 9,848,700.00 |
| 2023/24 | Approved | FOREIGN | 248,778,162.00 |
| 2023/24 | Approved | GOK | 9,848,700.00 |