Lot 4 - Construction of East and West of Nairobi Reticulation sewers

Project Detail Report

Overview

StatusOngoing
TypeReticulation sewers
AgencyAthi Water Works Development Agency
ProgramNairobi Rivers Basin Rehabilitation and Restoration Program: Sewerage Improvement Project Phase II
Progress61.80%

Location Information

CountyNairobi
ConstituencyDagoretti North
WardKawangware, Kilimani, Kileleshwa,Kabiro,Gatina
SettingUrban
Coordinates1.289000, 36.728100

Timeline & Impact

Start Date2021-09-03
Planned End Date2023-03-03
Actual End Date2024-12-02
ContractorChina road and Bridge Corporation in JVwith Hubei Shuizong water Resources & Hydropower Construction Co Ltd.
ConsultantHankuk Engineering Consultanta inJV with Ecosite Development Consultanta Ltd.
Target AreasKawangware, Kilimani, Kileleshwa,Kabiro,Gatina
Scope of Worksยท Laying of Reticulation sewers
ImpactsReduce pollution on Nairobi rivers. Restore Nairobi rivers. Contribute to improved health and quality of life through provision of safe and sustainable water and sewerage services.
Challengesdelay in issuance of the NEMA Licence and KPC Wayleave clearance to commence Karen Trunk wayleave
RemarksThe bank has yet to issue an update on the contractor's request for an extension of time

Project Cost

Total Contract Sum (GoK + Foreign)KES 76,883,159.00
GoK Contract SumKES 12,301,305.44
Foreign Contract SumKES 64,581,853.56
Cumulative ExpenditureKES 25,987,574.00
Outstanding CostKES 50,895,585.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 12,301,305.44
Adb Loan 64,581,853.56

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 713,030,232.40
2021/22 Approved GOK 64,820,930.22
2022/23 Approved FOREIGN 1,166,776,744.00
2022/23 Approved GOK 64,820,930.22
2023/24 Approved FOREIGN 2,667,381,278.00
2023/24 Approved GOK 64,820,930.22
2024/25 Allocated FOREIGN 1,637,376,697.00
2024/25 Allocated GOK 64,820,930.22

Beneficiaries

Target Households600
Target Population3,000