Construction Works for Kiambu -Ruaka Water and Sewerage Project

Project Detail Report

Overview

StatusOngoing
TypeWater supply, sewer laterals
AgencyAthi Water Works Development Agency
ProgramKenya Towns Sustainable Water Supply and Sanitation Programme
Progress98.04%

Location Information

CountyMurang'a
ConstituencyKiharu
WardMugoiri
SettingUrban
Coordinates-0.749474, 37.024614

Timeline & Impact

Start Date2019-01-07
Planned End DateN/A
Actual End DateN/A
ContractorChina Henan International Cooperation Grp Co. Ltd
ConsultantHoward Humphreys (east Africa) Ltd Consulting Engineers (Atkins)
Target AreasMugoiri
Scope of WorksLaying of 20.1km treated water main
ImpactsImprove the access, quality, availability and sustainability of water supply and wastewater management service
ChallengesDelay in processing payments Access to site particularly in the built up urban areas Part of the sewers were washed away during flooding
RemarksThere should be regular inspection along the pipelines to identify leakages at early stages. Also there should be increased support to area WSP to be able to address the issue on vandalism.

Project Cost

Total Contract Sum (GoK + Foreign)KES 699,378,463.80
GoK Contract SumKES 0.00
Foreign Contract SumKES 699,378,463.80
Cumulative ExpenditureKES 652,308,398.90
Outstanding CostKES 47,070,064.85

Funding Sources

SourceTypeAmount (KES)
Adb Loan 699,378,463.80

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2021/22 Approved FOREIGN 98,820,492.01
2022/23 Approved FOREIGN 147,715,200.00
2023/24 Approved FOREIGN 103,107,597.40
2024/25 Allocated FOREIGN 84,114,092.59

Beneficiaries

Target Households19,404
Target Population518,415