| Start Date | 2019-02-08 |
| Planned End Date | 2020-08-08 |
| Actual End Date | N/A |
| Contractor | Zhongding International Engineering Company Ltd & Jianxi Transporttation Engineering Group Corporation Kenya Ltd Jv |
| Consultant | Runji Consulting Group |
| Target Areas | Kiamwangi, Kiganjo, Ndarugo, Ng’enda |
| Scope of Works | Construction of 3 No. New Intakes and Water Treatment Plants in Handege, Ruabora, and Ng'enda whose capacity is 9,667m3/day, 4,280m3/day, and 4,280m3/day respectively. Laying 43 Km water transmission and distribution pipeline for Gatundu, Ng'enda, Mutomo, and Kenyatta Road Areas. 58 km of Trunk and laterals Sewers to serve Gatundu town and drain to Juja Sewerage Treatment Plant. Construction of the Gatundu Water and Sewerage Company Office Building. 2,000 Last Mile Sewerage Household Connections. |
| Impacts | Agumenting the water supply and improving wastewater disposal. |
| Challenges | Pemding Payments for sewerlines. delayed compensation of treated water lines. |
| Remarks | There should be regular inspection along the pipelines to identify leakages at early stages. Also there should be increased support to area WSP to be able to address the issue on vandalism. |