| Start Date | 2020-10-09 |
| Planned End Date | 2022-04-08 |
| Actual End Date | N/A |
| Contractor | China Civil Engineering Construction Corporstion Kenya Ltd |
| Consultant | Losai Management Limited |
| Target Areas | Kenol, KInyona, Kangari, Mareira , wangu |
| Scope of Works | 48.2 km, OD 200/160 mm transmission main in MUSWASCO area, 123 Km, OD 200-50 mm Last Mile Connectivity pipelines in MWESCO area, 24.3 Km, OD 90 mm Last Mile Connectivity pipelines in GATAWASCO area, 2 No. 250 m3 masonry tanks, INo. Ablution Block at Sabasaba market, 17km of 600/450/300mm dia. DWC trunk sewer pipelines, 15.1km of 250mm dia. DWC pipes of reticulation sewers, Sewage Treatment Plant of capacity 3,000m³/d,1,000 household connections; |
| Impacts | Access to water supply and improved sanitation services |
| Challenges | Pending payments for sewerlines, deelayed compensation for land at the intake, wayleave |
| Remarks | There should be regular inspection along the pipelines to identify leakages at early stages. Also there should be increased support to area WSP to be able to address the issue on vandalism. |