| Start Date | 2024-04-01 |
| Planned End Date | 2025-04-01 |
| Actual End Date | 2025-01-05 |
| Contractor | Visrom Company Limited |
| Consultant | Posch & Partners, Austria, with Norken International, Kenya |
| Target Areas | Kahara Sukari, Mwihoko, Kizito |
| Scope of Works | Construction of 7.2km Kahawa Sukari Mwihoko Ring mains, OD355-560, Laying of 2.3km Mwihoko East Ring mains, OD355-560, Laying of 68km distribution system to supply Mwihoko Area, OD63-160, Installing 1,400 Consumer Connections, Solarization of 10 No. boreholes |
| Impacts | provide a reliable water supply to over 50,000 residents, improving health and reducing water costs. Additionally, it will support economic growth and conserve water resources, contributing to the sustainable development of the region. |
| Challenges | Unforeseen circumstances along the Kahawa Sukari Avenue which affected the planned schedule. |
| Remarks | The Technical and Financial Appraisal for Lot 4 and Variation Order No. 1 were completed and sent to AWWDA for processing. The result of the Appraisal is that there is no change to the estimated final Contract Value of the Contract, including VO 01, compared with the Contract Amount. |