Kiambu Water Supply

Project Detail Report

Overview

StatusProposed
TypeWater Supply
AgencyAthi Water Works Development Agency
ProgramGovernment of Kenya Funded Development programme
Progress0.00%

Location Information

CountyKiambu
ConstituencyGithunguri
WardTing’ang’a, Ndumberi, Riabai, Township
SettingRural
Coordinates-1.056997, 36.777455

Timeline & Impact

Start DateN/A
Planned End DateN/A
Actual End DateN/A
ContractorPending Procurement
ConsultantCOWI/A.S Consultancy
Target AreasTing’ang’a, Ndumberi, Riabai, Township
Scope of WorksConstruction of 1 No. water intake, 6500m3/day. Construction of 7629m3/day WTP. Construction of 1No 6600m3/day reservoir. Laying of 55 km of distribution pipelines. Drilling of 10No. Boreholes and rehabilitation of 4No Boreholes provide 300KW solar power farm to operate the boreholes. Provision of NRW leakge detecton equipment, operating and Maintenance tools and Equipment.
ImpactsNil
ChallengesNil
RemarksNil

Project Cost

Total Contract Sum (GoK + Foreign)KES 118,792,749.00
GoK Contract SumKES 118,792,749.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Beneficiaries

Target Households49,426
Target Population165,232