Project Detail Report
| Status | Proposed |
|---|---|
| Type | Dam, Water Treatment, Water supply, sewer laterals, Sewer Treatment, Clean Energy |
| Agency | Athi Water Works Development Agency |
| Program | DSIF - Thika and Githunguri Water and Sanitation Project |
| Progress | 0.00% |
| County | Kiambu |
|---|---|
| Constituency | Githunguri |
| Ward | Githunguri, Githiga, |
| Setting | Urban |
| Coordinates | -1.097460, 36.739360 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | COWI/A.S Consultancy |
| Target Areas | of Works Contracted |
| Scope of Works | Construction of 1no. water intake 6500m3/day. Construction of 7620m3/day WTP. Construction of 1no. 6600m3/day resevoir. Laying of 55km distribution pipelines. Drilling of 10no. boreholes and rehabilitation of 4no. boreholes provide a 300KW solar power farm to operate the boreholes. |
| Impacts | >It will enhance people to live healthy lives with improved livelihoods and income opportunities. There will be an immense reduction in pollution of rivers and environmental degradation. It will promote renewable energy technologies that mitigate climate change and provide economic benefits. Improve the provision of services and institutional sustainability. |
| Challenges | N/A |
| Remarks | The designs are complete pending finalization of finance agreement |
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Danida | Loan | 17,238,643,380.00 |