Construction for Kabetee, Olesereni,West and South Nairobi Water and sewerage project
Project Detail Report
Overview
Status
Proposed
Type
Water supply, sewer
Agency
Athi Water Works Development Agency
Program
Nairobi Water and Sanitation Project
Progress
0.00%
Location Information
County
Nairobi
Constituency
Roysambu
Ward
Zimmerman, Roysambu
Setting
Urban
Coordinates
-1.217800, 36.887600
Timeline & Impact
Start Date
N/A
Planned End Date
N/A
Actual End Date
N/A
Contractor
N/A
Consultant
Artelia SAS and Mangut I.B Patel (MIBP) Ltd.
Target Areas
Zimmerman, Roysambu
Scope of Works
Laying a 19.6km transmission pipeline from Kabete-Olesereni and 8.5km from Gigiri-Karura-Outer Ring. Installing 53km water distribution pipeline and 3300Nr household connections. Construction of 2Nr storage tanks with capacity of 5,500m3 in Karen areas and 11000m3 in Uthiru. Laying of 175km of reticulation sewer lines.
Impacts
N/A
Challenges
N/A
Remarks
The designs are complete pending finalization of finance agreement