Project Detail Report
| Status | Proposed |
|---|---|
| Type | Water Supply and Sanitation |
| Agency | Athi Water Works Development Agency |
| Program | Nairobi Water and Sanitation Project |
| Progress | 0.00% |
| County | Nairobi |
|---|---|
| Constituency | Embakasi North |
| Ward | Kwa njenga, kwa Reuben, pipeline, imara daima, Kware,Kayole North, Kayole South, Komarock, Kariobangi south,dandora area 1, dandora area 11, dandora area 111 |
| Setting | Urban |
| Coordinates | -1.314915, 36.883158 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | Frame Consultants Ltd, Losai Management Ltd and Tertiary Consulting Engineers limited |
| Target Areas | informal settlements across Nairobi including Dandora, kariobangi, |
| Scope of Works | Develop sanitation strategies for the citywide inclusive sewered abd non-sewered sanitation(urban poor areas and peri-urban) that will inform activities to be incorporated in the preliminary design. Undertake conceptual and preliminary design of recommended options. Prepare capital investment cost estimates and financial and economic analysis of recommended options |
| Impacts | Aims to Develop an inclusive sanitation strategy for Nairobi City that addresses the entire sanitation value chain |
| Challenges | N/A |
| Remarks | N/A |
| Total Contract Sum (GoK + Foreign) | KES 134,238,836.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 134,238,836.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Adb | Grant | 134,238,836.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2021/22 | Approved | FOREIGN | 17,845,921.76 |
| 2022/23 | Approved | FOREIGN | 53,952,786.73 |
| 2022/23 | Approved | GOK | 1,037,553.59 |
| 2023/24 | Approved | FOREIGN | 38,202,723.22 |
| 2023/24 | Approved | GOK | 622,532.15 |
| Target Households | 412,529 |
|---|---|
| Target Population | 1,196,334 |