Kibera Soweto Chief's Camp

Project Detail Report

Overview

StatusOngoing
TypeBorehole, Water Supply
AgencyAthi Water Works Development Agency
ProgramDrilling & Equipping of 5No. Boreholes and Construction of 5No. Elevated Steel Water Tanks with Associated Water Distribution Networks. Lot 3
Progress1.00%

Location Information

CountyNairobi
ConstituencyLang'ata
WardLaini Saba
SettingUrban
Coordinates1.316700, 36.783300

Timeline & Impact

Start Date2020-05-06
Planned End Date2021-05-06
Actual End Date2021-05-06
ContractorExport Hydro Pump and Services (Africa) Limited
ConsultantN/A
Target AreasLaini Saba
Scope of WorksDrilling and Equipping of 1No. Borehole, construction of borehole chamber, pump house,water kiosk and associated water distribution network
ImpactsN/A
ChallengesFaulty Pumpset,Unstable power. Low Voltage.
RemarksNot Operational

Project Cost

Total Contract Sum (GoK + Foreign)KES 3,028,909.38
GoK Contract SumKES 3,028,909.38
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 2,861,934.17
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 3,028,909.38

Beneficiaries

Target Households300
Target Population1,500