Overview
| Status | Ongoing |
| Type | Borehole, Water Supply |
| Agency | Athi Water Works Development Agency |
| Program | Drilling & Equipping of 2No. Boreholes and Construction of 6No. Elevated Water Tanks with Associated Water Distribution Networks. Lot 6 |
| Progress | 1.00% |
Location Information
| County | Nairobi |
| Constituency | Lang'ata |
| Ward | Kibera |
| Setting | Urban |
| Coordinates | 1.316154, 36.793383 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Turn-O- Metal Engineers Ltd |
| Consultant | N/A |
| Target Areas | Kibera |
| Scope of Works | Drilling and equipping of borehole,Borehole chamber and pump house,Power Connection, 3No. Water Kiosk & Associated Piping and 1No. Elevated Tank |
| Impacts | N/A |
| Challenges | Faulty motor and pump. Requires replacement. |
| Remarks | Not Operational |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 266,438.00 |
| GoK Contract Sum | KES 266,438.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 266,438.00 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
266,438.00 |
Beneficiaries
| Target Households | 360 |
| Target Population | 1,800 |