Overview
| Status | Ongoing |
| Type | Water Supply |
| Agency | Athi Water Works Development Agency |
| Program | Construction of 8No. Elevated Steel Water Tanks in AWWDA Area. Lot 8 |
| Progress | 1.00% |
Location Information
| County | Nairobi |
| Constituency | Starehe |
| Ward | Muthurwa |
| Setting | Urban |
| Coordinates | 1.285835, 36.829021 |
Timeline & Impact
| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | David Engineering Limited |
| Consultant | N/A |
| Target Areas | Muthurwa |
| Scope of Works | Supply, delivery and installation of 18m Steel towers and 24m3 pressed steel tank |
| Impacts | N/A |
| Challenges | N/A |
| Remarks | Operational |
Project Cost
| Total Contract Sum (GoK + Foreign) | KES 1,469,271.46 |
| GoK Contract Sum | KES 1,469,271.46 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 830,515.43 |
| Outstanding Cost | KES 0.00 |
Funding Sources
| Source | Type | Amount (KES) |
| Gok |
Grant |
1,469,271.46 |
Beneficiaries
| Target Households | 720 |
| Target Population | 3,600 |