| Start Date | 2023-08-11 |
| Planned End Date | 2024-08-05 |
| Actual End Date | 2024-08-05 |
| Contractor | Upstrive Civil experts |
| Consultant | N/A |
| Target Areas | Khwisero |
| Scope of Works | Borehole Drilling and Capping of 1No at Khwisero TVCSupply and installation of 30m3 elevated steel tank, Installation of solar power hybrid system and submersible pump, Construction of 1nr normal water kiosk, Construction of 2nr CWPs, Rising main and distribution lines. |
| Impacts | Increased school attendance especially for girls as they now spend less time collecting water and managing sanitation needs. There is reduction in waterborne diseases due to access to clean water and improved sanitation which has led to better overall health and reduced healthcare costs. |
| Challenges | Insufficient budget allocation which led to delays and limitations in scope. Late disbursement of project funds |
| Remarks | The project is complete and functional. It is serving Kwisero Technical and Vocational Centre and center and the sorrounding communty |