| Start Date | 2024-03-01 |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Tsavo Merchant Ltd, Blueshift Tsavo Merchants Ltd and Hydrotech Associates Ltd |
| Consultant | N/A |
| Target Areas | Township |
| Scope of Works | mabanga chamber- sikata road pipeline (3,400m long,225mm diameter HDPE)
makutano at kanduyi junction to airstrip pipeline (2900m long 110mm and 300m long on 90mmdiameter HDPE from elevated tank to stadium)
airstrip pipeline to state lodge (600m long 110mm diameter HDPE)
pipeline to Makutano primary school tanks (600m long 90mm diameter HDPE)
sewer line- state lodge to Bungoma High School manhole
supply and installation of 2 no. 100m3 elevated structurally pressed steel tanks on steel towers
borehole drilling works
finishing works for the borehole drilling
installation of solar power hybrid system, solar flood light, and submersible pump
installation of 50m3 (50,000litres) pressed elevated steel tank on 8m steel tower
rising main from the borehole to elevated tank (30m length) 40mm dia
distribution line from the tank chamber (100m long) HDPE 90mm-50mm dia |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Insufficient budget allocation which led to delays and limitations in scope. Late disbursement of project funds |
| Remarks | Project complete and operational |