Khukolomani Health Centre Borehole Water project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramCross-County Programme
Progress70.00%

Location Information

CountyKakamega
ConstituencyKhwisero
WardKisa North
SettingRural
Coordinates0.139101, 34.538460

Timeline & Impact

Start Date2024-12-10
Planned End Date2025-06-10
Actual End DateN/A
ContractorHapex contractors limited & M/s Joyrowl Limited
ConsultantN/A
Target AreasKhukholomani
Scope of WorksInstallation of solar power hybrid system, solar flood light, and submersible pump supply and installation of 30m³ elevated structurally pressed steel tank on 10m steel tower rising main from the borehole to elevated tank (500m length) 40mm dia distribution line from the tank chamber (1600m long) hdpe 50mm-32mm dia construction of 4nr communal water points standard water kiosk
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesInsufficient budget allocation and late disbursement of project funds which led to delays
RemarksSlow progress of the project

Project Cost

Total Contract Sum (GoK + Foreign)KES 7,939,825.95
GoK Contract SumKES 7,939,825.95
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 2,218,680.00
Outstanding CostKES 188,398.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2022/23 Approved GOK 10,000,000.00

Beneficiaries

Target Households375
Target Population1,500