Project Detail Report
| Status | Proposed |
|---|---|
| Type | Water Supply |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Lake Victoria North WWDA Projects. |
| Progress | 0.00% |
| County | Vihiga |
|---|---|
| Constituency | Emuhaya |
| Ward | Central Bunyore Ward |
| Setting | Rural |
| Coordinates | 0.112890, 34.594279 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Nuram Consultants ltd |
| Consultant | N/A |
| Target Areas | Esinaka |
| Scope of Works | Rehabilitation Of 2no. 100m3 Masonry Sumps Electromechanical Works and Fencing Works Rising Main from The Pump House to Masonry Tank and Steel Tank (2000m Length) 110mm Dia HDPE Rehabilitation Of 1nr. Masonry 150m3 Tank And 1nr. 50m3 Elevated Steel Tank Return Line to Esirulo Dispensary 600m Length (OD 50mm Diameter HDPE) Construction Of 1no.Normal Water Kiosk at Esirulo Market Construction Of 5nr Communal Water Points Line To Esirulo Primary/Secondary/ Isanda Primary 1500m Length (OD 90mm-OD 63 Mm Diameter HDPE) Line To Esirulo Market 1300m Length (OD 140mm-63mm Diameter HDPE) Line To Mwiyavo Market 700m Length (OD 50mm Diameter HDPE) Line To Ikalikha Primary 1000m Length (OD 63mm Diameter HDPE) |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | No challenges yet |
| Remarks | Contractor has mobilised resources and ready to commence works. |
| Total Contract Sum (GoK + Foreign) | KES 13,847,568.78 |
|---|---|
| GoK Contract Sum | KES 13,847,568.78 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Source | Type | Amount (KES) |
|---|---|---|
| Gok | Grant | 15,000,000.00 |
| Fiscal Year | Stage | Funding Side | Amount (KES) |
|---|---|---|---|
| 2024/25 | Allocated | GOK | 15,000,000.00 |
| Target Households | 1,275 |
|---|---|
| Target Population | 5,100 |