| Start Date | N/A |
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | Kheiman Enterprises Limited |
| Consultant | No |
| Target Areas | Manyoni |
| Scope of Works | Protection of 2no springs
Construction of 30m3 masonry sump
Electromechanical works
Construction of pump house
Construction of rising main from the pumphouse to steel tank (1500m length) 63mm dia hdpe
Construction of 1nr. 30m3 pressed elevated steel tank on 8m high steel tower
Construction of normal water kiosk at manyonyi centre
Construction of line to manyonyi primary/secondary 2000m length (50mm-40mm)
Construction of offtake to market centre 500m length (40mm dia hdpe pipes)
Construction of offtake to manyonyi village 400m length (40mm dia hdpe pipes)
Construction of line to mahemas village 1200m length (50mm-40mm dia hdpe pipes)
Construction of communial water point (cwp) |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Late disbursement of funds |
| Remarks | project yet to start |