Borehole drilling and capping for Ainapng'etuny School Water Project

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramWater Harvesting Programme
Progress70.00%

Location Information

CountyNandi
ConstituencyNandi Hills
WardKapchorua
SettingRural
Coordinates0.021869, 35.356361

Timeline & Impact

Start Date2023-06-07
Planned End Date2023-08-07
Actual End Date2023-08-07
ContractorUpwork Enterprises Limited
ConsultantN/A
Target AreasAinapngetung
Scope of WorksDrilling and cappingInstallation of solar power hybrid system, solar flood light, and submersible pump supply and installation of 30m³ elevated structurally pressed steel tank on 10m steel tower rising main from the borehole to elevated tank (500m length) 40mm dia distribution line from the tank chamber (500m long) hdpe 50mm-32mm dia construction of 5nr communal water points
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesInsufficient budget allocation and late disbursement of project funds which led to delays
RemarksProject is almost complete

Project Cost

Total Contract Sum (GoK + Foreign)KES 2,934,664.00
GoK Contract SumKES 2,934,664.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 1,904,585.00
Outstanding CostKES 159,263.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 10,000,000.00

Beneficiaries

Target Households375
Target Population1,500