| Start Date | 2024-04-11 |
| Planned End Date | 2024-10-11 |
| Actual End Date | N/A |
| Contractor | Amtaf Investment Ltd |
| Consultant | N/A |
| Target Areas | Etenje |
| Scope of Works | Drilling, Installation of solar power hybrid system, solar floodlight and submersible pump
Supply and installation of 18m³ elevated structurally pressed steel tank on 10m steel tower
Rising main from the borehole to elevated tank (100m length) 40mm dia
Construction of 3nr communal water points
Distribution line from the tank to cwp2 (130m long) 40mm-32mm dia |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Insufficient budget allocation which led to delays and limitations in scope and late disbursement of funds |
| Remarks | Slow progress |