Water storage facility at Kapkatenyi Pri. Sch

Project Detail Report

Overview

StatusOngoing
TypeBorehole
AgencyLake Victoria North Water Works Development Agency
ProgramLake Victoria North WWDA Projects.
Progress40.00%

Location Information

CountyBungoma
ConstituencyMt. Elgon
WardKapkateny
SettingRural
Coordinates0.801147, 34.622421

Timeline & Impact

Start Date2024-04-11
Planned End Date2024-10-11
Actual End DateN/A
ContractorRaslan Investment Limited
ConsultantN/A
Target AreasKapkateny
Scope of WorksGravity line to masonry tank 300m length (100mm DIA), 100m3 masonry tank, Ndarut distribution line 1600m length (100mm - 32mm DIA), Chebin distribution lines 1700m length, Sacha distribution line 1400m length and Communal water point
ImpactsReduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities
ChallengesInsufficient budget allocation which led to delays and limitations in scope and late disbursement of funds
RemarksSlow progress

Project Cost

Total Contract Sum (GoK + Foreign)KES 8,648,663.00
GoK Contract SumKES 8,648,663.00
Foreign Contract SumKES 0.00
Cumulative ExpenditureKES 0.00
Outstanding CostKES 0.00

Funding Sources

SourceTypeAmount (KES)
Gok Grant 10,000,000.00

Budget Allocations by Fiscal Year

Fiscal YearStageFunding SideAmount (KES)
2023/24 Approved GOK 5,000,000.00

Beneficiaries

Target Households122
Target Population1,600