| Start Date | 2024-04-11 |
| Planned End Date | 2024-10-11 |
| Actual End Date | N/A |
| Contractor | Raslan Investment Limited |
| Consultant | N/A |
| Target Areas | Kapkateny |
| Scope of Works | Gravity line to masonry tank 300m length (100mm DIA), 100m3 masonry tank, Ndarut distribution line 1600m length (100mm - 32mm DIA), Chebin distribution lines 1700m length, Sacha distribution line 1400m length and Communal water point |
| Impacts | Reduction in waterborne diseases due to access to clean water and improved sanitation, leading to better overall health and reduced healthcare costs. Increased school attendance especially for girls as they spend less time collecting water and managing sanitation needs. Access to clean water and sanitation will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | Insufficient budget allocation which led to delays and limitations in scope and late disbursement of funds |
| Remarks | Slow progress |