Project Detail Report
| Status | Proposed |
|---|---|
| Type | Water Supply |
| Agency | Lake Victoria North Water Works Development Agency |
| Program | Engineering Procurement Construction-Finance |
| Progress | 0.00% |
| County | N/A |
|---|---|
| Constituency | N/A |
| Ward | N/A |
| Setting | Urban |
| Coordinates | 0.282188, 34.754070 |
| Start Date | N/A |
|---|---|
| Planned End Date | N/A |
| Actual End Date | N/A |
| Contractor | N/A |
| Consultant | N/A |
| Target Areas | All |
| Scope of Works | Intake works and WTP Hydro power component Water supply in kakamega Water supply in bungoma county Sanitation components in Kakamega town and Peri- urban areas Sanitation components in Bungoma town and Peri- urban areas Sanitation components in Webuye town and Peri- urban areas |
| Impacts | There will be reduction in waterborne diseases due to access to clean water leading to better overall health and reduced healthcare costs. There will be increased school attendance especially for girls as they spend less time collecting water. Access to clean water will increase productivity in the workforce, leading to improved livelihoods and economic growth, women and girls often bear the burden of collecting water, so improved water access will empower them and provide more time for other activities |
| Challenges | N/A |
| Remarks | The feasibility study was prepared seeking for funds |
| Total Contract Sum (GoK + Foreign) | KES 0.00 |
|---|---|
| GoK Contract Sum | KES 0.00 |
| Foreign Contract Sum | KES 0.00 |
| Cumulative Expenditure | KES 0.00 |
| Outstanding Cost | KES 0.00 |
| Target Households | 904,412 |
|---|---|
| Target Population | 3,617,648 |